Step 1 (Preparation)
Ensure that the wall the insulation is free from wallpaper, any signs of condensation and any indications that damp may be present. If there is wallpaper present, please make sure it is removed before adding insulation to a wall. Try to avoid using steam to remove wallpaper as that can add condensation to a room, if steam is required to remove the wallpaper, then please leave for one to two days before applying insulation to ensure the insulation does not trap any condensation. If there is a painted wall, again try to scratch the surface of the wall which again allows the insulation to be placed against the original plaster rather than a coat of paint at all points. 100% coverage of all outer walls must be ensured, thus avoiding any risk of cold bridging.

No parge coat is required on any wall prior to the installation of the Ezy-Fit Green IWI system however the wall must be dry and free from any damp or risk of damp.

Plan the installation of all timber studs so that you are avoiding any risk of drilling through embedded electricity cables or pipes. Ensure surface mounted services have been checked by a suitably competent person to ensure adding the insulation will not compromise safety and their performance. If required, reroute electrical services to on top of the
insulation should this be requested by a suitably qualified individual. Always ensure services are safe to work near or around before any work commences.

Remove all curtains, radiators, and electrical outlet fronts, ensuring that these are removed by a professional who can disconnect services from them first and make it safe to work in that area.

At this point should the work area be thoroughly prepared you can focus on adding the insulation to the walls. This preparation would also include the marking position of any pattress boxes so that not covered by timber studs.

Care shall be taken in the overall design and construction of junctions with other elements and openings to ensure a 100% coverage of outer walls is maintained with the installation of the system.

Step 2
Create the frame for the system by loosely screw fixing 100x50mm timber studs horizontally to the floor and ceiling level of the existing wall, then vertically at 570mm centres & horizontally at 1200 mm centres, ensuring the vertical studs are cut and installed so as to be in close contact with the horizontal studs.

Step 3
Remove the timber studs from the wall, mark on the side of the stud the location of the hole, to locate position when timber backer has been affixed, and cut strips of our hemp stud backer to size, and affix to the back of the timber studs with our stainless-steel fixing, ensuring full coverage of the stud with insulation. Premark by cutting or scoring a cross on the hemp where the fixing for the timber will pass through, so that the drill bit does not come into contact with the insulation, eliminating the risk of it catching and tearing.

Step 4
Re affix the timber studs, with the hemp stud backer attached to the wall. The studs should always be installed with the hemp stud backer against the substrate.

Step 5
– Pressure fit the hemp or wood fibre batt between the studs, completely filling the insulation zone and ensuring there are no gaps between the batt and studs. Where the hemp batts require cutting, they should be cut 10mm wider than the space they intend to fill.

Step 6
Install the membrane (to the warm side of the insulation) with stainless steel fixings into the timber studs. Tape all edges and planes down to create the airtight layer and seal any penetrations in the membrane with appropriate tape.

Step 7
Install the membrane (to the warm side of the insulation) with stainless steel fixings into the timber studs. Tape all edges and planes down to create the airtight layer and seal any penetrations in the membrane with appropriate tape.

Step 8
Seal all planes, edges, and joints of plasterboard our IWI sealant (polyacrylate-base adhesive sealant for plasterboard which is blue in colour) this is high mortality sealant, to prevent air leakage.

Step 9
Check all trunked air vents to verify they are clear and unobstructed; apply mastic sealant around windows, door frames, etc.

Step 10
Fixing Radiators – All fixtures can be re-fitted the studs with appropriate fixings.

Picture rails and Dado Rails – These can be fixed back onto the plastered finish with either silicon or Grab adhesive. Pictures and light weight fixings – Can be fitted using the relevant plasterboard fixing.

Electrical Cables – These are usually within the wall however these can be pulled through the Green IWI system to surface mount the sockets. Cables with a high amp rating such as cookers, electric car chargers and showers need to be routed by a fully trained and competent Electrician. If there are high amperage cables that are surfaced mounted, we recommend consultation with a qualified Electrician who can advise of any requirements to have those cables moved to the outside of the insulation.

Walls & Ceilings are more straight forward but the installer must ensure the space above a ceiling and below the floor above has sufficient insulation added to avoid any potential cold bridging. If access is not available from above them, we recommend accessing this area from below as a skim of plaster will be used across the wall and this, along with plasterboard can “make good” any area accessed from the ceiling.

Areas of limited space
To assist with these areas, you can also use Ezy Fit reveal board which assists in areas where the standard Green IWI system cannot physically be used. We always recommend using the full system build up in all cases but understand there are limitations to space at times and using a reveal board is far better than no insulation at all. We recommend a full bed of adhesive plus mechanical fixing be used if a reveal board is the only solution due to space issues.

Combustion appliances
It is imperative that ventilation requirements of gas, oil or coal fired combustion appliances are not compromised by the installation of Ezy Fit Green IWI system and that the system does not interfere with the supply of fresh air to the appliance. Recommendations, guidance, and compliance to building regulations for the ventilation of combustion appliances can be found in building regulations and must be adhered to.

High amperage cables
Always consult with a qualified Electrician when dealing with high amperage cables that may be impacted by the addition of insulation to an outer wall. Insulation added to the outer cover of an electricity cable can reduce its performance so we would always recommend using professionals to either move a high amperage cable or confirm its suitability to be “wrapped” by the insulation.

Water and Gas pipes
As with the electricity running within the house you may also have services such as gas and water that need to be considered before adding insulation. We always recommend using the professional services of a suitably qualified engineer to ascertain what is required in dealing with these service pipes. If in doubt always utilise the services of a Competent and suitably qualified person when dealing with gas, water, and electricity.

Flues
Care must always be taken to ensure that flues and ventilation measures for all appliances are not blocked or in any way compromised. Always check with the manufacturer if in doubt.