Generic filters
Filter by Categories
Get a quote

Guides and datasheets

Preparation

Installation – Roof Dry Lining

Last updated August 2026

Step 1
Insulation board should be placed below the rafters with no air gap between the boards and the already existing insulation boards between the rafters or ceiling joists.

Step 2
The framing should be set at a maximum of 600 mm centres, and the framing should be wide enough to provide at least a 19 mm bearing in order to support each board edge. Noggins or straps will be required at the perimeter. When the joists/rafters are set at 600 mm centres, additional noggins or straps will be required perpendicular to the main framing in order to provide the necessary support for board edges

Step 3
The system should be cut to allow for a 5 mm height clearance and fixed using plasterboard nails located at 150 mm centres for timber only or drywall screws located at 230 mm centres maximum for timber or metal framing. Penetration depths into the framework should be a minimum of 25 mm for timber or 10 mm for metal.

Where residual loft spaces exist and can be accessed through existing or newly formed hatches in the studwork dwarf walls. A visual inspection of the areas should be carried out to check for the presence of either downlighters or high amperage cables, supplying cookers or electric showers Should downlighters be present, these must be covered with fire rated downlighter covers, themselves then covered with a minimum of 300mm loft roll Where high amperage cables are present, these must not be covered by insulation and should be left in position upon the top layer of insulation.


An assessment of the existing loft insulation depth (if any) should be made.

  1. Loft roll should then be laid to an overall depth of not less than 300mm to all horizontal areas within the roof space, cross-laid to ensure joist heads are covered by the top layer of insulation.
  2. Any other exposed horizontal timbers such as purlins should also be covered to prevent cold bridging It is essential that the eaves of the roof space are adequately ventilated to prevent moisture build up and condensation. Having assessed the ventilation at survey stage, the installer should follow the recommendation of the survey and install, where necessary and required, the appropriate ventilation system Any exposed pipework or water storage tanks must be insulated. The residual areas must be insulated using a mineral wool product that complies with BS EN 13162, which is the British Standard for factory-made mineral wool products used in thermal insulation for buildings.