Generic filters
Filter by Categories
Get a quote

Guides and datasheets

Retrofit Guidance

Avoiding Damp

Last updated August 2026

When you wrap a building you can accidentally trap an issue that has gone unnoticed for years. The importance of a good survey and correction ventilation. We recommend a PAS (Publicly Available Specification) Assessor and Coordinator be used as they are trained in ensuring all properties are correctly ventilated when additional insulation is added to a property. We would always recommend having a professional damp report carried out if in any doubt.

Any damp present should be eradicated with the assurance that it will not return once insulation is added. This needs to be carried out prior to insulation being added to a property. This action plus the inclusion of correct 

Thermal bridging

Thermal bridging  occurs when the continuity of the insulation is broken, causing the inner surface of the wall at that point to become much cooler than the surface where the wall is insulated. This can often occur at the junction of a wall and separating floor. Thermal bridging can cause an increase in heat loss, surface condensation and mould growth and can often be a problem in terraced houses. We recommend installing M IWI between the ceiling and floor area of the first floor along the length of the external wall to avoid any further cold bridges.

Areas of Limited Space. 

To assist with these areas, you can also use Ezy Fit reveal board which assists in areas where the standard M IWI Slab cannot physically be used. We always recommend using a full M IWI slab in all cases but understand there are limitations to space at times and using a reveal board is far better than no insulation at all. We recommend a full bed of adhesive plus mechanical fixing be used if a reveal board is the only solution due to space issues. 

Floor voids and below ground floor insulation. 

As with all voids that occur between the ceiling and floor we recommend lifting the end floorboard and securing M-IWI slabs to the inside of each outer wall. These slabs are essential in ensuring that the voids between ceiling and floor is not going to create a cold bridge and thus cause damage to the property as well as breaking the impact of the insulation provided across the rest of the property. For sub floor voids we recommend that no insulation is added below a damp proof course in a way that could “bridge” any future damp that arises.

Surface condensation
Occurs when water vapour in the air cools and condenses (reverts to liquid form) as it encounters colder surfaces. Reducing the amount of water vapour in the air by extracting moist air from kitchens and bathrooms and increasing the surface temperature will prevent condensation forming on the internal surface of solid external walls. The installation of the Ezy Fit M IWI system will raise the surface temperature of the walls to a level whereby condensation will not form under usual maximum humidity conditions experienced in dwellings.

Combustion appliances
It is imperative that ventilation requirements of gas, oil or coal fired combustion appliances are not compromised by the installation of Ezy Fit M IWI system and that the system does not interfere with the supply of fresh air to the appliance. Recommendations, guidance, and compliance to building regulations for the ventilation of combustion appliances can be found in building regulations and must be adhered to.

High amperage cables
Always consult with a qualified Electrician when dealing with any electrical cables but especially high amperage cables that may be impacted by the addition of insulation to the inside of an outer wall. Insulation added to the outer cover of an electricity cable can reduce its performance and could in certain circumstances raise the temperature of a cable, thus creating a high-risk situation, so we would always recommend using professionals to either move a high amperage cable or confirm its suitability to be “wrapped” by the insulation.

Water and Gas pipes
As with the electricity running within the house you may also have services such as gas and water that need to be considered before adding insulation. We always recommend using the professional services of a suitably qualified engineer to ascertain what is required in dealing with these service pipes.

If in doubt always utilise the services of a Competent and suitably qualified person when dealing with gas, water, and electricity.

Flues
Care must always be taken to ensure that flues and ventilation measures for all appliances are not blocked or in any way compromised. The A1 Fire rating makeup of Ezy Fit M IWI Wall slab means they can be placed next to the outer side of a flue but should never compromise its operation. Always check with the manufacturer if in doubt.

Damp Proof Couse (DPC)
The Ezy Fit M IWI System should always be installed above a working damp proof course. In no way should the M IWI wall slab compromise or bridge a DPC as this will lead to greater problems at a later date. We always recommend an injection DPC if no DPC is in place or if the DPC is compromised and cannot be rectified with standard building methods. If IWI is to extend below external ground level, then follow guidance in BS 8102:2009 Code of practice for protection of below ground structures against water from the ground

Party Walls
Thermal Junctions can occur when insulation is not continuous. A party or adjoining wall is an area that can create a thermal junction. Whilst returning the insulation on a party wall can mitigate the thermal bridging, care must be taken if insulating along a cold party wall which could in theory make the wall colder and increase the risk of cold or damp that is already there if the neighbour’s property is not heated or correctly ventilated.

Acoustic qualities of the Ezy Fit M IWI system
The M IWI slabs fitted to a wall improve the comfort of a wall by reducing noise however when using reveal board there is the potential of reducing the original acoustic qualities of a wall through vibration. In instances where acoustic performance is reduced, we would recommend a mineral wool thermal laminate board be used. Ask Ezy Fit and we will be able to supply these readily.

We cannot stress enough the importance of the property being:

  • Professionally surveyed, both inside and outside and deemed suitable for the internal wall insulation to be fitted. If the property is not found to be suitable, please do not fit the system until a professional deems that any repairs have been carried out and potential damp is fully removed prior to work commencing.
  • That all services are treated with the respect they demand and professionally assessed to ensure they can complement the building whilst these services are in their current position and if deemed unsuitable, the services may need to be moved prior to work commencing.
  • That a professionally created ventilation strategy is in place 
  • That the homeowner is aware of the ongoing visual checks and minimal maintenance required to ensure the Internal wall insulation system performs as it was designed to.
  • A condensation risk analysis shall be completed at the project-specific design stage for all elements of the construction, including at junctions, openings and penetrations, to minimise the risk of surface and interstitial condensation. When correctly installed on an occupied building, no condensation will form on the internal wall.
  • For Very Severe Exposure Zones (Zone 4) or if the property is designated a high risk of external water penetration, in accordance with BRE Report 262, the Specifier shall integrate the ventilation strategy for the building into the design and consider wind-driven rain and permeability of existing materials by modelling, using WUFI Analysis.