Installation


Create the frame for the system by loosely screw fixing 100mm timber studs horizontally to the floor and ceiling level of the existing wall, then vertically at 600mm centres & horizontally at 1200 mm centres, ensuring the vertical studs are cut and installed to be in close contact with the horizontal studs.
Re affix the timber studs, with the MW stud backer attached to the wall. The studs should always be installed with the MW stud backer against the substrate.
Fixing 100mm x 50mm timber studs to the substrate with a 40mm x 100mm MW Stud backer attached.



Pressure fit the MW batt between the studs, completely filling the insulation zone and ensuring there are no gaps between the batt and studs. Where the MW batts require cutting, they should be cut 10mm wider than the space they intend to fill. We would also advise the us of an insulation saw, which can also be provided by Ezy Fit.





Install the membrane (to the warm side of the insulation) with stainless steel fixings into the timber studs. Tape all edges and planes down to create the airtight layer and seal any penetrations in the membrane with appropriate tape.



Fit a 12.5mm plasterboard (BS EN 520) by screwing into the timber studs using drywall or wood screws and cover the entire face of the installed insulation system.



Seal all perimeter and any penetrations of plasterboard with our IWI sealant (polyacrylate-base adhesive sealant for plasterboard which is blue in colour) this is high mortality sealant, to prevent air leakage. Scrim tape to aid in plastering can be added after sealing.
When installing the Ezy Fit M IWI System, you may encounter areas of the substrate were fitting the full 100mm thickness just isn’t practical. This is most common in stairwells or staircases, inward opening doors or even built in wardrobes and cupboards.
The Ezy Fit reveal Boards are also used in the windowsills and cheeks, where the full thickness of insulation could be greater than that of the UPVC frames.
For these ‘areas of limited space’, you can also use Ezy Fit Insulated Reveal Board (12.5mm) which assists in areas where the standard M IWI system cannot physically be used. We always recommend using the full system build up in all cases but understand there are limitations to space at times and using a reveal board is far better than no insulation at all. We recommend a full bed of adhesive plus mechanical fixing be used if a reveal board is the only solution due to space issues.
Maintenance
Once installed, the System requires simple maintenance. For 60-year durability, a bespoke extended repair and maintenance protocol will apply. For advice in respect of repair and maintenance, consult the Agrément holder.
The maintenance schedule for the installed System can be carried out by the person living in the home as no specialist tools or training is required. This is no different from the maintenance required without the insulation being added to each room.
- For signs of damaged areas and cracks in the plaster, if spotted please use household filler to repair them. If the sealant around windows is perishing, please replace as you would today.
- Signs of damp, discoloration, or black mould should always be reported to the Company that fitted your IWI System.
- Don’t forget to always check for signs of deterioration and cracks in the pointing mortar or render of the external wall of your home.
If in doubt the person living in the home should contact the Installer of the Ezy-Fit M IWI system.