Dorma Cheeks and Ceilings

- Dormer cheeks must be insulated using MI BOARD, following the same installation procedure as detailed for the sloping
ceilings. - Where the thickness of the board would extend beyond the thickness of any window frames, the board should be
chamfered to allow it to finish within the window frame depth. - MI BOARD must be fitted to the stud wall beneath the dormer window. Where the windowsill protrusion is insufficient,
the sill must be extended using a uPVC profile section. - Dormer ceilings, whether sloping or flat, must be insulated using MI BOARD, following the same installation procedure as
above. - Seal any penetrations and all plane edges with a MI SEAL sealant to prevent air leakage.